Violation Detail
Standard Cited: 19260451 F04 General requirements.
Inspection Nr: 1247161.015
Citation: 01002B
Citation Type: Serious
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $3,049.00
Current Penalty: $0.00
Issuance Date: 01/09/2018
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 01/22/2018
Gravity: 5
Report ID: 0317000
Contest Date:
Final Order: 05/24/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/24/2018 | $0.00 | 01/22/2018 | Serious | |
Penalty | Z: Issued | 01/09/2018 | $3,049.00 | 01/22/2018 | Serious |
Text For Citation: 01 Item/Group: 002B Hazard:
29 CFR 1926.451(f)(4): Part(s) of a scaffold that were damaged or weakened, such that the scaffold's strength was less than that required by paragraph (a) of this section, were not immediately repaired, replaced, braced to meet those provisions, nor removed from service until repaired. a) Jobsite: The cross brace use to provide stability and structural integrity for the scaffold was not attached to the frame and the employer allowed employees to work from the scaffold exposing them to scaffold collapse hazards. Condition was observed on or about 12 JULY 2017.