Violation Detail
Standard Cited: 19100119 D03 I B Process safety management of highly hazardous chemicals.
Inspection Nr: 1151337.015
Citation: 01002B
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $12,471.00
Current Penalty: $0.00
Issuance Date: 11/15/2016
Nr Instances: 2
Nr Exposed: 110
Abatement Date: 05/25/2019
Gravity:
Report ID: 0214200
Contest Date: 12/08/2016
Final Order: 03/05/2018
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 03/05/2018 | $0.00 | 05/25/2019 | Other | |
| Penalty | C: Contested | 12/13/2016 | $12,471.00 | 12/29/2016 | Serious | |
| Penalty | Z: Issued | 11/15/2016 | $12,471.00 | 12/29/2016 | Serious |
Text For Citation: 01 Item/Group: 002B Hazard:
29 CFR 1910.119(d)(3)(i)(B): Information pertaining to equipment in the process did not include Piping and Instrumentation Diagrams (P&IDs): a) Yard 5 Tk-5057 The employer did not ensure that information pertaining to process equipment was included on P&ID F-3226 when valves 5057-I1.2 and 5057-IB.1 on the butane injection process were observed to be car sealed closed in the field and not marked as such on the P&ID. b) Chem South Tank 12646 The employer did not ensure that information pertaining to process equipment was included on P&ID B1-80600-646 when a nitrogen pressure gauge, nitrogen regulator, conservation vent/pressure relieve valve, and temperature thermometer were installed on the tank in the field and not marked as such on the P&ID. Violations observed on or about 5/17/2016.