Standard Cited: 19100023 A02 Ladders.
Inspection Nr: 315860635
Citation: 01002A
Citation Type: Serious
Abatement Status: I
Initial Penalty: $2,550.00
Current Penalty: $1,913.00
Issuance Date: 11/08/2011
Nr Instances: 1
Nr Exposed: 10
Abatement Date: 11/11/2011
Gravity: 01
Report ID: 0213900
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 12/05/2011 | $1,913.00 | 11/11/2011 | Serious | |
| Penalty | Z: Issued | 11/08/2011 | $2,550.00 | 11/11/2011 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard: REFINERY
29 CFR 1910.23 (a)(2) Every ladderway floor opening or platform was not guarded by a standard railing with standard toeboard on all exposed sides (except at entrance to opening), with the passage through the railing either provided with a swinging gate or so offset that a person could not walk directly into the opening. a) Polyester production plant between finishers: A swinging gate with a standard railing was not provided at the entrance to the waste pit, on or about 10/3/11.