Violation Detail
Standard Cited: 19100147 C04 II B The control of hazardous energy (lockout/tagout).
Inspection Nr: 1712464.015
Citation: 01002A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $16,131.00
Current Penalty: $16,131.00
Issuance Date: 04/10/2024
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 05/28/2024
Gravity: 10
Report ID: 0112600
Contest Date:
Final Order: 05/03/2024
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 04/10/2024 | $16,131.00 | 05/28/2024 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1910.147(c)(4)(ii)(B): The energy control procedures did not clearly and specifically outline the steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy: 38 Jackson Rd, Devens, MA: On and before October 24, 2023, employees utilized the Water For Injection 831 draft energy control procedure (ECP) that did not include all energy sources required to reach a zero energy state. A missing electrical energy source hazard was identified during a September 2023 preventive maintenance event, but was not added to the procedure until November 29, 2023. Additionally, this draft ECP did not identify or include steps to isolate the machine's thermal and pneumatic energy sources. On October 24, 2023, a Metrology Technician received burn injuries from uncontrolled pressurized steam thermal energy while removing a pressure transmitter from this machine.