Standard Cited: 19260651 J02 Specific Excavation Requirements.
Inspection Nr: 1706495.015
Citation: 01002A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $3,457.00
Current Penalty: $3,457.00
Issuance Date: 04/18/2024
Nr Instances: 4
Nr Exposed: 2
Abatement Date: 05/14/2024
Gravity: 5
Report ID: 0627100
Contest Date:
Final Order: 05/23/2024
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/23/2024 | $3,457.00 | 05/14/2024 | Serious | |
| Penalty | Z: Issued | 04/18/2024 | $3,457.00 | 05/14/2024 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1926.651(j)(2): Protection was not provided by placing and keeping excavated or other materials or equipment at least 2 feet (.61m) from the edge of excavations, or by the use of retaining devices that were sufficient to prevent materials or equipment from falling or rolling into excavations, or by a combination of both if necessary: On or about October 27, 2023, and at times prior to, employees were engaged in work activities related to installation of pipe in a trench, where the following: a) At the western side of the trench spoil pile was not at least 2-feet from the edge of the excavation. b) At the air condition unit, the spoil pile was not at least 2-feet from the edge of the excavation. c) At the eastern side, the spoil pile was not at least 2-feet from the edge of the excavation. d) At the western side by the manhole vault, the spoil pile was not at least 2-feet from the edge of the excavation.