Violation Detail
Standard Cited: 19260600 A06 I Equipment.
Inspection Nr: 1690070.015
Citation: 01002A
Citation Type: Serious
Abatement Date: 03/01/2024 2
Initial Penalty: $12,421.00
Current Penalty: $9,316.00
Issuance Date: 02/05/2024
Nr Instances: 1
Nr Exposed: 8
Related Event Code (REC): A
Gravity: 10
Report ID: 0626700
Contest Date:
Final Order: 04/01/2024
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 04/01/2024 | $9,316.00 | 03/01/2024 | Serious | |
Penalty | Z: Issued | 02/05/2024 | $12,421.00 | 03/01/2024 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1926.600(a)(6)(i): For lines rated 50kV or below, a minimum of 10 feet was not maintained between the energized line and the equipment: a) On or about August 9, 2023, an excavator operated by Harper Brothers Construction, LLC, the general contractor, was operated within 10 feet of overhead power lines carrying approximately 1.2kV of electricity, exposing R&A Boring LLC employees to electrocution hazards.