Violation Detail
Standard Cited: 19100147 C04 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1679248.015
Citation: 01002A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $15,625.00
Current Penalty: $15,625.00
Issuance Date: 11/29/2023
Nr Instances: 1
Nr Exposed: 25
Abatement Date: 12/26/2023
Gravity: 10
Report ID: 1032500
Contest Date:
Final Order: 01/04/2024
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 01/04/2024 | $15,625.00 | 12/26/2023 | Serious | |
Penalty | Z: Issued | 11/29/2023 | $15,625.00 | 12/26/2023 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section: (a) Press #38: On or about June 21, 2023 and at times prior, energy control procedures had not been developed for the Mitsubishi 950 ton injection molding machine. Workers remove stuck parts by standing in-between mold units.