Violation Detail
Standard Cited: 19100147 D02 The control of hazardous energy (lockout/tagout).
Inspection Nr: 1635750.015
Citation: 01002A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,278.00
Current Penalty: $15,625.00
Issuance Date: 02/08/2023
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 02/23/2023
Gravity: 5
Report ID: 0523300
Contest Date:
Final Order: 03/01/2023
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 03/01/2023 | $15,625.00 | 02/23/2023 | Serious | |
| Penalty | Z: Issued | 02/08/2023 | $12,278.00 | 02/23/2023 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1910.147(d)(2): The machine or equipment was not turned off or shut down using the procedures established for the machine or equipment. a) On or about November 20, 2022, at the previously addressed inspection site, employees adjusting wooden pallets at the pallet infeed magazine and palletizer of the Poly 12 stacker were exposed to unexpected energization, start-up, or release of stored energy because the machine or equipment was not turned off or shut down before adjusting the wooden pallets.
Translate