Violation Detail
Standard Cited: 19100217 B13 Mechanical power presses.
Inspection Nr: 1550212.015
Citation: 01002A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $10,513.00
Current Penalty: $5,000.00
Issuance Date: 11/22/2021
Nr Instances: 1
Nr Exposed: 30
Abatement Date: 01/11/2022
Gravity: 10
Report ID: 0522000
Contest Date:
Final Order: 12/07/2021
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/07/2021 | $5,000.00 | 01/11/2022 | Serious | |
Penalty | Z: Issued | 11/22/2021 | $10,513.00 | 01/11/2022 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1910.217(b)(13): Control reliability. When required by paragraph (c)(5) of this section, the control system shall be constructed so that a failure within the system does not prevent the normal stopping action from being applied to the press when required, but does prevent initiation of a successive stroke until the failure is corrected. The failure shall be detectable by a simple test, or indicated by the control system. This requirement does not apply to those elements of the control system which have no effect on the protection against point of operation injuries. (a) On or about August 26, 2021, an employee was injured at the point of operation of Federal #7 partial revolution 80 ton press Serial #7-653 due to the lack of a control reliability system, such as but not limited to check valve, anti-repeat feature, anti-tie down feature, and multiple relays.