Violation Detail
Standard Cited: 19100269 D07 III Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1500643.015
Citation: 01002A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $10,728.00
Current Penalty: $7,510.00
Issuance Date: 04/22/2021
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 06/15/2021
Gravity: 5
Report ID: 0418200
Contest Date:
Final Order: 05/27/2021
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/27/2021 | $7,510.00 | 06/15/2021 | Serious | |
| Penalty | Z: Issued | 04/22/2021 | $10,728.00 | 05/18/2021 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
1910.269(d)(7)(iii) After lockout or tagout devices have been removed and before a machine or equipment is started, affected employees were not notified that the lockout or tagout devices have been removed. a) Lake Oliver Dam: On or about 10/27/2020, employer exposed employees to caught-in hazards, in that procedures for notifying affected employees when lock out was removed from the penstock priming valve prior to placing system back into operation was not followed.