Violation Detail
Standard Cited: 19260451 B01 I General requirements.
Inspection Nr: 1479381.015
Citation: 01002A
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $4,048.00
Current Penalty: $2,428.80
Issuance Date: 06/23/2020
Nr Instances: 1
Nr Exposed: 3
Abatement Date:
Gravity: 10
Report ID: 0418800
Contest Date:
Final Order: 07/23/2020
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/23/2020 | $2,428.80 | Serious | ||
Penalty | Z: Issued | 06/23/2020 | $4,048.00 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1926.451(b)(1)(i): Each platform unit (e.g., scaffold plank, fabricated plank, fabricated deck, or fabricated platform) was not installed so that the space between adjacent units and the space between the platform and the uprights were no more than 1 inch (2.5 cm) wide, except where the employer can demonstrate that a wider space is necessary: On or about 6/11/2010, at jobsite located at 9500 SW 61st Ct, Pinecrest, FL 33156, employees were exposed to the hazard of falling up to 18'-0" to ground level while working from tubular welded frame scaffolds that were not fully planked.