Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1402844.015
Citation: 01002A
Citation Type: Other
Abatement Date: 12/16/2019 2
Initial Penalty: $6,630.00
Current Penalty: $6,630.00
Issuance Date: 11/19/2019
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC): R
Gravity:
Report ID: 0317300
Contest Date: 12/09/2019
Final Order: 03/30/2020
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/30/2020 | $6,630.00 | 12/16/2019 | Other | |
Penalty | C: Contested | 12/09/2019 | $6,630.00 | 12/16/2019 | Serious | |
Penalty | Z: Issued | 11/19/2019 | $6,630.00 | 12/16/2019 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: a) Concrete Mixing Tower - On or about May 23, 2019, the employer failed to ensure that a periodic inspection of the general energy control procedure contained within their written Energy Control Program (Lockout/Tagout Program), was conducted at least annually. Abatement Note: a. Where lockout is used for energy control, the periodic inspection shall include a review, between the inspector and each authorized employee, of that employee's responsibilities under the energy control procedure being inspected.1910.147(c)(6)(i)(D) b. Where tagout is used for energy control, the periodic inspection shall include a review, between the inspector and each authorized and affected employee, of that employee's responsibilities under the energy control procedure being inspected, and the elements set forth in paragraph (c)(7)(ii) of this section.1910.147(c)(6)(ii) c. The employer shall certify that the periodic inspections have been performed. The certification shall identify the machine or equipment on which the energy control procedure was being utilized, the date of the inspection, the employees included in the inspection, and the person performing the inspection.