Violation Detail
Standard Cited: 19260416 A03 General requirements.
Inspection Nr: 1397906.015
Citation: 01002A
Citation Type: Serious
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $4,376.00
Current Penalty: $3,500.80
Issuance Date: 10/09/2019
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 10/16/2019
Gravity: 10
Report ID: 0317000
Contest Date:
Final Order: 10/30/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 10/30/2019 | $3,500.80 | 10/16/2019 | Serious | |
Penalty | Z: Issued | 10/09/2019 | $4,376.00 | 10/16/2019 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1926.416(a)(3): Before work began, the employer did not ascertain by inquiry, direct observation, or by instruments, whether any part of an energized electric power circuit, exposed or concealed, was so located that the performance of the work could bring any person, tool, or machine into physical or electrical contact with the electric power circuit: a) Jobsite: 2245-47 Wilder Street, Philadelphia, PA 19146, platform on side brackets beneath 1st working platform on 2nd level, left side facing 23rd street - Prior to conducting masonry operations, the employer did not ascertain whether his employees could come into physical contact with any part of an electrical power circuit at the site through the performance of their work . Employees working from a supported tubular welded frame scaffold were within 1 -3 feet of an overhead power line and service drop line.a) Jobsite: 2245-47 Wilder Street, Philadelphia, PA 19146, platform on side brackets beneath 1st working platform on 2nd level, left side facing 23rd street - Prior to conducting masonry operations, the employer did not ascertain whether his employees could come into physical contact with any part of an electrical power circuit at the site through the performance of their work . Employees working from a supported tubular welded frame scaffold were within 1 -3 feet of an overhead power line and service drop line. Noted on or about 4/12/19.