Standard Cited: 19260251 A01 Rigging equipment for material handling.
Inspection Nr: 1359217.015
Citation: 01002A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $6,630.00
Current Penalty: $4,100.00
Issuance Date: 03/27/2019
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 04/02/2019
Gravity: 5
Report ID: 0524200
Contest Date:
Final Order: 04/18/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 04/18/2019 | $4,100.00 | 04/02/2019 | Serious | |
Penalty | Z: Issued | 03/27/2019 | $6,630.00 | 04/02/2019 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1926.251(a)(1): Rigging equipment for material handling was not inspected prior to use on each shift and as necessary during its use to ensure that it was safe: a) On November 8, 2018, during the removal of roof debris, the employer did not ensure all rigging was inspected prior to use and removed from service when found defective.