Violation Detail
Standard Cited: 19100269 M03 II Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1313494.015
Citation: 01002A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,805.00
Current Penalty: $12,805.00
Issuance Date: 08/24/2018
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 09/20/2018
Gravity: 10
Report ID: 0627510
Contest Date: 09/19/2018
Final Order: 05/04/2020
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | R: Review Commission | 05/04/2020 | $12,805.00 | 09/20/2018 | Serious | |
| Penalty | C: Contested | 09/20/2018 | $12,805.00 | 09/20/2018 | Serious | |
| Penalty | Z: Issued | 08/24/2018 | $12,805.00 | 09/20/2018 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1910.269(m)(3)(ii): The employer did not ensure that all switches, disconnectors, jumpers, taps, and other means through which known sources of electric energy may be supplied to the particular lines and equipment to be denenergized were open. The employer did not render such means inoperable, unless its design does not so permit, and then sure that such means are tagged to indicate that employees are at work: On or about May 2, 2018, employees performing repair work on an overhead power line were exposed to electrical hazards when the employer did not ensure that all switches were open.