Standard Cited: 19260416 A03 General requirements.
Inspection Nr: 1170955.015
Citation: 01002A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,471.00
Current Penalty: $8,729.00
Issuance Date: 01/12/2017
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 02/01/2017
Gravity: 10
Report ID: 0626700
Contest Date:
Final Order: 02/07/2017
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 02/07/2017 | $8,729.00 | 02/01/2017 | Serious | |
| Penalty | Z: Issued | 01/12/2017 | $12,471.00 | 02/01/2017 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1926.416(a)(3): Before work began the employer did not ascertain by inquiry, direct observation, or by instruments, whether any part of an energized electric power circuit concealed, was so located that the performance of the work could bring a person into physical or electrical contact with the energized electric power circuit: a) On or about August 17, 2016, in classroom number 105, Area A, where the employer had not ascertained the presence of energized conductors concealed above ceiling tiles prior to troubleshooting an outlet.