Violation Detail
Standard Cited: 19260451 B01 General requirements.
Inspection Nr: 1047982.015
Citation: 01002A
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $2,800.00
Current Penalty: $2,800.00
Issuance Date: 05/06/2015
Nr Instances: 1
Nr Exposed: 4
Abatement Date:
Gravity: 10
Report ID: 0418600
Contest Date:
Final Order: 06/04/2015
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 05/06/2015 | $2,800.00 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii) a) At 554 East Beach Blvd Gulf Shores, Alabama: On or about March 18, 2015 and at times prior; the employer failed to ensure that section one of a four buck high scaffold on the south side was fully planked exposing employees to a fall hazard of 19.1 feet to the ground below. b) At 554 East Beach Blvd Gulf Shores, Alabama: On or about March 18, 2015 and at times prior; the employer failed to ensure that section two of a four buck high scaffold on the south side was fully planked exposing employees to a fall hazard of 19.3 feet to the ground below. c) At 554 East Beach Blvd Gulf Shores, Alabama: On or about March 18, 2015 and at times prior; the employer failed to ensure that scaffold section three of a four buck high scaffold on the south side was fully planked exposing employees to a fall hazard of 19.3 feet to the ground below. d) At 554 East Beach Blvd Gulf Shores, Alabama: On or about March 18, 2015 and at times prior; the employer failed to ensure that scaffold section four of a four buck high scaffold on the south side was fully planked exposing employees to a fall hazard of 19.3 feet to the ground below.