Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 989898.015
Citation: 01002
Citation Type: Serious
Abatement Date: 09/30/2015 2
Initial Penalty: $4,950.00
Current Penalty: $2,475.00
Issuance Date: 02/06/2015
Nr Instances: 4
Nr Exposed: 18
Related Event Code (REC):
Gravity: 5
Report ID: 0524200
Contest Date: 03/06/2015
Final Order: 10/15/2015
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 10/15/2015 | $2,475.00 | 09/30/2015 | Serious | |
Penalty | C: Contested | 03/11/2015 | $4,950.00 | 03/05/2015 | Serious | |
Penalty | Z: Issued | 02/06/2015 | $4,950.00 | 03/05/2015 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed. a) Facility wide - The employer did not ensure that periodic inspections of the energy control procedures were conducted at least annually to ensure that the procedures and requirements of the energy control program were properly implemented and followed by employees.