Violation Detail

Standard Cited: 19260652 E02 I Requirements for protective systems.

Inspection Nr: 967256.015

Citation: 01002

Citation Type: Serious

Abatement Status: Corrected During Inspection

Initial Penalty: $2,380.00

Current Penalty: $1,666.00

Issuance Date: 05/14/2014

Nr Instances: 1

Nr Exposed: 2

Abatement Date:

Gravity: 5

Report ID: 0522000

Contest Date:

Final Order: 06/03/2014

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty I: Informal Settlement 06/03/2014 $1,666.00   Serious  
Penalty Z: Issued 05/14/2014 $2,380.00   Serious  

Text For Citation: 01 Item/Group: 002 Hazard:

29 CFR 1926.652(e)(2)(i): Excavation of material to a level no greater than 2 feet (.61m) below the bottom of the members of a support system was permitted where the system was not designed to resist the forces calculated for the full depth of the trench: -Employees were working in an excavation that was measured to be 8'-0" in depth with the trench shield located 4'-2" from the bottom of the excavation, exposing employees to a potential cave in hazard.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.