Violation Detail
Standard Cited: 19100303 B06 General.
Inspection Nr: 963338.015
Citation: 01002
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $4,050.00
Current Penalty: $2,400.00
Issuance Date: 05/02/2014
Nr Instances: 4
Nr Exposed: 176
Abatement Date: 05/14/2014
Gravity: 5
Report ID: 0418600
Contest Date:
Final Order: 05/22/2014
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/22/2014 | $2,400.00 | 05/14/2014 | Serious | |
| Penalty | Z: Issued | 05/02/2014 | $4,050.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.303(b)(6): Conductors or equipment not identified for use in a damp or wet location were used: a) North Wall of the Shipping Area: On or about March 12, 2014, the employer did not ensure a 4 receptacle outlet had ground fault circuit interrupter (GFCI) protection which exposed employees to electric shock hazards. b) South Wall of the IQF Area: On or about March 12, 2014, the employer did not ensure a 4 receptacle outlet had ground fault circuit interrupter (GFCI) protection which exposed employees to electric shock hazards. c) West Wall of the IQF Area: On or about March 12, 2014, the employer did not ensure a 2 receptacle outlet in series had ground fault circuit interrupter (GFCI) protection which exposed employees to electric shock hazards. d) Trim Station of the Kill Area: On or about March 12, 2014, the employer did not ensure four 2 receptacle outlets in series had ground fault circuit interrupter (GFCI) protection which exposed employees to electric shock hazards.