Violation Detail
Standard Cited: 19260451 C03 General requirements.
Inspection Nr: 961406.015
Citation: 01002
Citation Type: Serious
Abatement Date: 10/31/2014 2
Initial Penalty: $2,800.00
Current Penalty: $500.00
Issuance Date: 07/03/2014
Nr Instances: 3
Nr Exposed: 7
Related Event Code (REC):
Gravity: 10
Report ID: 0213900
Contest Date: 07/31/2014
Final Order: 12/01/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 12/01/2014 | $500.00 | 10/31/2014 | Serious | |
Penalty | C: Contested | 08/01/2014 | $2,800.00 | 07/12/2014 | Serious | |
Penalty | Z: Issued | 07/03/2014 | $2,800.00 | 07/12/2014 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.451(c)(3): Supported scaffold poles, legs, post, frames, and/or uprights were not plumb and braced to prevent swaying and displacement: a) 104 Emerson Court, southern most unit, end unit - Employees were working approximately 16 feet above the ground, from a pump jack scaffold without proper bracing or equivalent means (poles were braced only at the roof), on or about 03/05/14; b) 104 Emerson Court, unit #3, northern most scaffold setup-Employees were working approximately 7 feet above the ground, from a pump jack scaffold with poles bearing on a scrapped piece of siding, on or about 03/05/14; c) 104 Emerson Court, scaffold setup on the south end of building - Employees were working approximately 12 feet above the ground, from a pump jack scaffold with poles bearing on a scrapped piece of siding, on or about 03/05/14. NOTE: IN ADDITION TO ABATEMENT CERTIFICATION, THE EMPLOYER IS REQUIRED TO SUBMIT ABATEMENT DOCUMENTATION FOR THIS ITEM, FAILURE TO COMPLY WILL RESULT IN AN ADDITIONAL PENALTY OF $1000.00 IN ACCORDANCE WITH 29 CFR 1903.19.