Violation Detail
Standard Cited: 19100305 A02 XI Wiring methods, components, and equipment for general use.
Inspection Nr: 960756.015
Citation: 01002
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $3,740.00
Current Penalty: $2,000.00
Issuance Date: 07/21/2014
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 08/15/2014
Gravity:
Report ID: 0627500
Contest Date:
Final Order: 08/11/2014
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 08/11/2014 | $2,000.00 | 08/15/2014 | Other | |
| Penalty | Z: Issued | 07/21/2014 | $3,740.00 | 07/25/2014 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.305(a)(2)(xi): Cable assemblies and flexible cords and cables were not supported in place at intervals that ensure that they will be protected from physical damage: Drill site: on or about February 25, 2014, the 480 volt overhead wires running from the active pit to the premix pit were left hanging low. This condition exposed the electrical conductors to potential physical damage and employees to electrical shock hazards.