Violation Detail
Standard Cited: 19100212 A01 General requirements for all machines.
Inspection Nr: 947491.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $3,825.00
Current Penalty: $2,677.50
Issuance Date: 11/29/2013
Nr Instances: 5
Nr Exposed: 5
Abatement Date: 01/07/2014
Gravity: 5
Report ID: 0521100
Contest Date:
Final Order: 12/23/2013
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/23/2013 | $2,677.50 | 01/07/2014 | Serious | |
Penalty | Z: Issued | 11/29/2013 | $3,825.00 | 01/07/2014 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.212(a)(1): One or more methods of machine guarding was not provided to protect the operator and other employees in the machine area from hazards such as those created by point of operation, ingoing nip points, rotating parts, flying chips and sparks: a) Injection molding machines #33 & #34 did not have the ejection chute area of the machines guarded to prevent access to the mold dies during operation. b) Hurco VM1, serial VM1-06018083BEA and Hurco BMC, serial OHT9001025B were being operated without interlocked guard doors to prevent entry during machine operation. c) The #81 fully electric injection molding machine had an unguarded opening in the ejection area of approximately 18" x 35", permitting access to the die area during operation. ABATEMENT CERTIFICATION REQUIRED