Violation Detail
Standard Cited: 19260102 A01 Eye and face protection.
Inspection Nr: 920622.015
Citation: 01002
Citation Type: Serious
Abatement Date: 08/22/2013 2
Initial Penalty: $1,600.00
Current Penalty: $960.00
Issuance Date: 08/16/2013
Nr Instances: 2
Nr Exposed: 2
Related Event Code (REC):
Gravity: 5
Report ID: 0316100
Contest Date:
Final Order: 11/07/2013
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 11/07/2013 | $960.00 | 08/22/2013 | Serious | |
Penalty | Z: Issued | 08/16/2013 | $1,600.00 | 08/22/2013 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.102(a)(1): Eye and face protective equipment were not used when machines or operations presented potential eye or face injury from physical, chemical, or radiation agents: a) Exterior Front of Structure - A laborer was observed pouring a bag of Roanoke Masonry Cement that contained Portland Cement, into a mortar mixer, and was not wearing eye protection, on or about 07/18/13. b) Exterior Front of Structure - A brick layer was observed striking wet mortar joints which contained Portland Cement, and was not wearing eye protection, on or about 07/18/13. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.