Violation Detail
Standard Cited: 19260451 C02 V General requirements.
Inspection Nr: 914974.015
Citation: 01002
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $6,300.00
Current Penalty: $1,550.00
Issuance Date: 09/27/2013
Nr Instances: 1
Nr Exposed: 2
Abatement Date:
Gravity: 10
Report ID: 0214200
Contest Date:
Final Order: 11/08/2013
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 11/08/2013 | $1,550.00 | Serious | ||
| Penalty | Z: Issued | 09/27/2013 | $6,300.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.451(c)(2)(v): The employer used forklifts to support scaffold platforms without ensuring that the entire platform was attached to the fork and that the forklift was not moved horizontally while the platform was occupied: Note: Preamble to Subpart L promulgated new paragraph (c)(2)(iv) & (v) in final rule to provide guidance. Added provision requires that in the case of fork-lifts, the entire scaffold platform be secured to the forklift. a. The Enclave at Short Hills - 2 Short Hills Avenue, Short Hills, NJ - Building 7 The employer lifted sub-contractor employees engaged in residential framing activities in a supported scaffold platform, which was not attached to the Gradall All-terrain Forklift to attach fascia to the building structure. Violation observed on or about August 26, 2013
Translate