Violation Detail
Standard Cited: 19100303 B01 II General.
Inspection Nr: 914523.015
Citation: 01002
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $3,300.00
Current Penalty: $1,500.00
Issuance Date: 09/30/2013
Nr Instances: 2
Nr Exposed: 4
Abatement Date: 01/19/2015
Gravity:
Report ID: 0418300
Contest Date: 10/21/2013
Final Order: 11/17/2014
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 11/17/2014 | $1,500.00 | 01/19/2015 | Other | |
Penalty | C: Contested | 10/28/2013 | $3,300.00 | Serious | ||
Penalty | Z: Issued | 09/30/2013 | $3,300.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.303(b)(1)(ii): Electrical equipment was not free from recognized hazards, based on the mechanical strength and durability, including, for parts designed to enclose and protect other equipment, the adequacy of the protection thus provided: (a) On or about 06/26/13 - Saw #1, the protective conduit was broken on the supply conduit, exposing the insulated wires. (b) On or about 06/26/13 - Forklift charging station, the protective conduit was broken on supply conduit, exposing the insulated wires.