Violation Detail
Standard Cited: 19260416 A03 General requirements.
Inspection Nr: 77380.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $4,200.00
Current Penalty: $3,000.00
Issuance Date: 09/02/2011
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 09/26/2011
Gravity: 10
Report ID: 0524500
Contest Date:
Final Order: 09/20/2011
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 09/20/2011 | $3,000.00 | 09/26/2011 | Serious | |
| Penalty | Z: Issued | 09/02/2011 | $4,200.00 | 09/26/2011 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.416(a)(3): Before work began, the employer did not ascertain by inquiry, direct observation, or by instruments, whether any part of an energized electric power circuit, exposed or concealed, was so located that the performance of the work could bring any person, tool, or machine into physical or electrical contact with the electric power circuit: Employees operating an aerial lift were exposed to electrical hazards. The employer did not ascertain that the employees would be working in proximity to energized electric power lines.