Violation Detail
Standard Cited: 19261402 C01
Inspection Nr: 686058.015
Citation: 01002
Citation Type: Serious
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $5,500.00
Current Penalty: $5,500.00
Issuance Date: 04/04/2013
Nr Instances: 1
Nr Exposed: 9
Abatement Date: 04/10/2013
Gravity: 5
Report ID: 0111400
Contest Date: 05/02/2013
Final Order: 01/01/2014
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 01/01/2014 | $5,500.00 | 04/10/2013 | Serious | |
Penalty | C: Contested | 05/09/2013 | $5,500.00 | 04/10/2013 | Serious | |
Penalty | Z: Issued | 04/04/2013 | $5,500.00 | 04/10/2013 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.1402(c)(1): 29 CFR 1926.1402(c)(1): The employer did not ensure that ground preparations necessary to meet the requirements in pargraph (b) were provided. Jobsite: The company did not ensure that ground conditions were adequate for the crane company. The crane was used to hoist National Grid materials and personnel.