Violation Detail
Standard Cited: 19100184 F01 Slings.
Inspection Nr: 622018.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $1,200.00
Current Penalty: $720.00
Issuance Date: 11/26/2012
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 12/14/2012
Gravity: 1
Report ID: 0830500
Contest Date:
Final Order: 12/10/2012
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 12/10/2012 | $720.00 | 12/14/2012 | Serious | |
| Penalty | Z: Issued | 11/26/2012 | $1,200.00 | 12/14/2012 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.184(f)(1): Wire rope sling(s) were used with loads in excess of rated capacities shown in Tables N1843 through N18414: (a) Nidi Tec Inc at 5686 Logan Ct Unit C, Denver, CO 80216: On and before July 3, 2012, the employer used wire rope slings for moving bundles of slabs. The slings did not have tags showing their rated weight capacity. This condition potentially exposes employees to struck-by and crushing hazards. Abatement Note: Abatement certification is required for this item (see enclosed Certification of Corrective Action Worksheet).
Translate