Violation Detail
Standard Cited: 19100333 C03 III A Selection and use of work practices
Inspection Nr: 470638.015
Citation: 01002
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $2,800.00
Current Penalty: $2,800.00
Issuance Date: 12/05/2012
Nr Instances: 1
Nr Exposed: 1
Abatement Date:
Gravity: 10
Report ID: 0111700
Contest Date:
Final Order: 12/17/2012
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 12/17/2012 | $2,800.00 | Serious | ||
| Penalty | Z: Issued | 12/05/2012 | $2,800.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.333(c)(3)(iii)(A): Vehicles or mechanical equipment capable of having parts of their structures elevated near energized overhead lines were not operated so that a clearance of 10 feet (305 cm) was maintained: a. Job site - The truck crane was operating with the rope closer than 10 feet from overhead lines.
Translate