Violation Detail
Standard Cited: 19260405 J05 VIII Wiring methods, components, and equipment for general use.
Inspection Nr: 451108.015
Citation: 01002
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $3,000.00
Current Penalty: $3,000.00
Issuance Date: 06/28/2012
Nr Instances: 1
Nr Exposed: 1
Abatement Date:
Gravity: 1
Report ID: 0316100
Contest Date:
Final Order: 07/26/2012
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 06/28/2012 | $3,000.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.405(j)(5)(viii): Materials were stored in transformer vaults: a) Temporary Electrical Shed, Conex Box - A superintendent and other workers were using the temporary electrical shed where combustible materials were observed stored on top of a 277 volt transformer creating an electrical and a fire hazard exposing them to an electrical hazard, on or about 05/30/12.