Violation Detail
Standard Cited: 19100119 D03 IB Process safety management of highly hazardous chemicals.
Inspection Nr: 315144956
Citation: 01002
Citation Type: Serious
Abatement Status: X
Initial Penalty: $4,200.00
Current Penalty: $2,520.00
Issuance Date: 04/19/2012
Nr Instances: 6
Nr Exposed: 4
Abatement Date: 08/31/2012
Gravity: 10
Report ID: 0111400
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/02/2012 | $2,520.00 | 08/31/2012 | Serious | |
| Penalty | Z: Issued | 04/19/2012 | $4,200.00 | 06/05/2012 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard: CHEMNEP
29 CFR 1910.119(d)(3)(i)(B): Process safety information pertaining to the equipment in the process did not include the piping and instrument diagrams (P&ID'S): LOCATION: FACILITY: The employer did not ensure that the P&ID's were accurate and up to date. Instance A) Not all of the system components were identified on the P&ID's. Instance B) Not all system component symbols on the P&ID were listed and identified in the key. Instance C) Several system components were either identified incorrectly or not identified at all.