Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 314918392
Citation: 01002
Citation Type: Serious
Abatement Status: X
Initial Penalty: $2,295.00
Current Penalty: $1,147.50
Issuance Date: 09/19/2011
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 11/03/2011
Gravity: 01
Report ID: 0112300
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 10/14/2011 | $1,147.50 | 11/03/2011 | Serious | |
| Penalty | Z: Issued | 09/19/2011 | $2,295.00 | 11/03/2011 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard: CHEMNEP
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: Facility: The employer did not ensure that authorized employees were evaluated annually on the Machine Specific Procedures.