Violation Detail
Standard Cited: 19100023 C01 Ladders.
Inspection Nr: 314767104
Citation: 01002
Citation Type: Serious
Abatement Date: 03/31/2011 X
Initial Penalty: $2,500.00
Current Penalty: $2,500.00
Issuance Date: 03/14/2011
Nr Instances: 1
Nr Exposed: 23
Related Event Code (REC):
Gravity: 05
Report ID: 0625700
Contest Date: 04/04/2011
Final Order: 04/11/2012
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 03/14/2011 | $2,500.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard: REFINERY
29 CFR 1910.23(c)(1): Open sided floor(s) or platform(s), 4 feet or more above the adjacent floor or ground level, were not guarded by standard railings (or th e equivalent as specified in 29 CFR 1910.23(e)(3)(i) through (v), on all open si des.: The employer does not ensure all platforms 4 feet or more above adjacent f loor or ground level are guarded by a standard railing. A section of the midrail approximately 36 inches in length was missing from the overhead platform of the D-102 Crude Desalter creating a fall hazard of approximately (8) feet. This vio lation was observed on or about October 1, 2010. Pursuant to 29 CFR 1903.19, wit hin ten (10) calendar days of the abatement date, the employer must submit docum entation showing that it is in compliance with the standard, including describin g the steps that it is taking to ensure that employees are not being exposed to a fall hazard.