Violation Detail
Standard Cited: 19100119 D03 II Process safety management of highly hazardous chemicals.
Inspection Nr: 313759920
Citation: 01002
Citation Type: Other
Abatement Date: 04/01/2011 X
Initial Penalty: $5,000.00
Current Penalty:
Issuance Date: 01/18/2011
Nr Instances: 4
Nr Exposed: 19
Related Event Code (REC): I
Gravity: 10
Report ID: 0213100
Contest Date:
Final Order:
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 02/07/2011 | 04/01/2011 | Other | ||
Penalty | Z: Issued | 01/18/2011 | $5,000.00 | 02/22/2011 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard: CHEMNEP
29 CFR 1910.119(d)(3)(ii): The employer did not document that the equipment in the process complied with recognized and generally accepted good engineering practices: (a)Resin Process Area, 7k reactor and associated equipment: Piping & Instrumentation Diagrams (P&IDs) were not complete, in that process equipment and instruments, including but not limited to: valves, pumps, pipes, logic controllers, and instruments, were not properly identified on the P&IDs, on or prior to 8/6/10. Pursuant to 29 CFR 1903.19(c), the employer must provide certification and documentation to OSHA that this violation has been abated within 10 calendar days of the "Date by which Violation Must be Abated".