Violation Detail
Standard Cited: 19100119 D03 IB Process safety management of highly hazardous chemicals.
Inspection Nr: 313137804
Citation: 01002
Citation Type: Serious
Abatement Status: X
Initial Penalty: $7,000.00
Current Penalty: $4,900.00
Issuance Date: 09/14/2011
Nr Instances: 1
Nr Exposed: 500
Abatement Date: 01/31/2012
Gravity: 10
Report ID: 0523300
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 09/28/2011 | $4,900.00 | 01/31/2012 | Serious | |
| Penalty | Z: Issued | 09/14/2011 | $7,000.00 | 09/27/2011 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard: CHEMNEP
29 CFR 1910.119(d)(3)(i)(B): Process safety information pertaining to the equipment in the process did not include the piping and instrument diagrams (P&ID'S): The P&IDs for the ammonia refrigeration system were not accurate to the as built condition of the system, including but not limited to: a) Frick #1 compressor, 1 1/2" LIOC line; b) Frick #1 compressor, 1/2" PO line; c) Frick #1 compressor, pressure relief valve on shell and tube oil cooler;
Translate