Standard Cited: 19100119 D03 IB Process safety management of highly hazardous chemicals.

Inspection Nr: 313137804

Citation: 01002

Citation Type: Serious

Abatement Status: X

Initial Penalty: $7,000.00

Current Penalty: $4,900.00

Issuance Date: 09/14/2011

Nr Instances: 1

Nr Exposed: 500

Abatement Date: 01/31/2012

Gravity: 10

Report ID: 0523300

Contest Date:

Final Order:

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty I: Informal Settlement 09/28/2011 $4,900.00 01/31/2012 Serious  
Penalty Z: Issued 09/14/2011 $7,000.00 09/27/2011 Serious  

Text For Citation: 01 Item/Group: 002 Hazard: CHEMNEP

29 CFR 1910.119(d)(3)(i)(B): Process safety information pertaining to the equipment in the process did not include the piping and instrument diagrams (P&ID'S): The P&IDs for the ammonia refrigeration system were not accurate to the as built condition of the system, including but not limited to: a) Frick #1 compressor, 1 1/2" LIOC line; b) Frick #1 compressor, 1/2" PO line; c) Frick #1 compressor, pressure relief valve on shell and tube oil cooler;

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.