Standard Cited: 19100119 J02 Process safety management of highly hazardous chemicals.
This violation item has been deleted.
Inspection Nr: 311913552
Citation: 01002
Citation Type: Serious
Abatement Status:
Initial Penalty: $5,000.00
Current Penalty:
Issuance Date: 10/09/2008
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 11/21/2008
Gravity: 10
Report ID: 0213400
Contest Date: 10/30/2008
Final Order: 03/23/2009
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | R: Review Commission | 03/23/2009 | 11/21/2008 | Serious | ||
| Penalty | J: ALJ Decision | 12/16/2008 | 11/21/2008 | Serious | ||
| Penalty | Z: Issued | 10/09/2008 | $5,000.00 | 11/21/2008 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard: REFINERY
29 CFR 1910.119(j)(2): The employer did not establish and implement written procedures to maintain the on-going mechanical integrity of process equipment: a) ABW - The employer did not implement written procedures for the installation of epoxy coatings to the interior surfaces of piping. Such procedures shall include proper surface preparation, adequate number of coats and cure times between coatings, thickness measurement of coatings and necessary verification/documentation. On 04/09/08 approximately 2500 lbs. of butane was released from a hole in the E- 17C exchanger outlet piping. The epoxy lining on the interior of the pipe spool had failed allowing corrosion of the carbon steel pipe.