Standard Cited: 5A0001 OSH Act General Duty Paragraph

Inspection Nr: 309337160

Citation: 01002

Citation Type: Serious

Abatement Status: X

Initial Penalty: $500.00

Current Penalty: $350.00

Issuance Date: 08/24/2007

Nr Instances: 1

Nr Exposed: 30

Abatement Date: 10/12/2007

Gravity: 02

Report ID: 0336000

Contest Date:

Final Order:

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty I: Informal Settlement 09/17/2007 $350.00 10/12/2007 Serious  
Penalty Z: Issued 08/24/2007 $500.00 10/12/2007 Serious  

Text For Citation: 01 Item/Group: 002 Hazard: CRUSHING

Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employmnent and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to accidents related to hoist failures and falling loads resulting Struck-by/caught- between hazards and related crush and blunt force trauma injuries: A.) Centrifugal Molding Area/-ton Jib Crane #53806/On or About April 25, 2007: The Ingersoll Rand hoist was not equipped with an upper limit over travel device. The Jib Crane and its associated hoist were utilized for work activities that included but were not limited to the construction of centrifugal molds. The Jib Crane's hoist lifted loads that weighed approximately 200 to 500-pounds. Reference: ASME Standard B30.16 Overhead Hoists -Section 16-1.2.14 B.) US Bronze Foundry & Machine, Inc. ---- Hoists: As of August 22, 2007, hoists were being utilized with deficiencies that were identified in the contractor crane/hoist inspection report which was generated in March of 2007. These deficiencies included but were not limited to control cable issues, brake adjustments, pendant labeling, and wire rope issues. Reference: ASME Standard B30.16 Overhead Hoists - Section 16-2.3.3 (a) Abatement Note: Among other methods, feasible and acceptable means to correct the conditions noted above include: 1.Install commercially available upper limit switch as specified and depicted in ANSI/ASME B30.16. 2.Utilize the crane inspection contractor's inspection reports to develop, implement, and follow an abatement plan for the correction of all hoist deficiencies.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.