Violation Detail

Standard Cited: 5A0001 OSH Act General Duty Paragraph

Inspection Nr: 303683593

Citation: 01002

Citation Type: Serious

Abatement Status: X

Initial Penalty: $2,500.00

Current Penalty: $1,500.00

Issuance Date: 06/06/2001

Nr Instances: 2

Nr Exposed: 14

Abatement Date: 06/13/2001

Gravity: 10

Report ID: 0626000

Contest Date:

Final Order:

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty I: Informal Settlement 06/27/2001 $1,500.00 06/13/2001 Serious  
Penalty Z: Issued 06/06/2001 $2,500.00 06/13/2001 Serious  

Text For Citation: 01 Item/Group: 002 Hazard: CRUSHING

Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to a collapsed mast (derrick) hazard: The hazard of collapsed mast (derrick) of a drilling rig resulting from failure to install wire rope guylines with correctly installed Crosby clips on all four sides of the rig as recommended by the manufacturer's specifications for the safe guying of the mast to ensure adequate anchorage in the following: a.Two guylines incorrectly installed Crosby clips. b.Geronimo emergency escape line incorrectly installed Crosby clips. This occurred on April 5, 2001 on Cleere Drilling Company Rig # 18. Among other abatement, one feasible and acceptable abatements method to correct this hazard would be installation of a properly secured guylines as specified in the American Petroleum Institute second edition, paragraph 3.14 of spec 4e and American Petroleum Institute Standard 4d sixth edition paragraph 3.4 and 4f, appendix C16,first edition May 01, 1985. Essential elements of this procedures would include: 1.Hand screwed in auger anchors into soil to the manufacturer's recommended specifications. 2.Wire rope guylines properly secured to the raised portion of the auger anchor. 3.Also correctly install and properly secure the Crosby clips to the ends of the wire rope guylines.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.