Violation Detail
Standard Cited: 19100269 D06 VII Electric Power Generation, Transmission, and Distribution.
This violation item has been deleted.
Inspection Nr: 1845076.015
Citation: 01002
Citation Type: Serious
Abatement Status:
Initial Penalty: $16,550.00
Current Penalty: $0.00
Issuance Date: 01/30/2026
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 02/26/2026
Gravity: 10
Report ID: 0830500
Contest Date: 02/26/2026
Final Order: 04/10/2026
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 04/10/2026 | $0.00 | 02/26/2026 | Serious | |
| Penalty | C: Contested | 02/26/2026 | $16,550.00 | 02/26/2026 | Serious | |
| Penalty | Z: Issued | 01/30/2026 | $16,550.00 | 02/26/2026 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.269(d)(6)(vii): Before starting work on machines or equipment that have been locked out or tagged out, the authorized employee shall verify that isolation and deenergizing of the machine or equipment have been accomplished. If normally energized parts will be exposed to contact by an employee while the machine or equipment is deenergized, a test shall be performed to ensure that these parts are deenergized: a) On or about August 18, 2025, the controlling employer did not ensure employees and subcontracted employees were protected from arc flash explosion hazards. Commissioning technicians engaged in the group lockout of the PCS 025 (SG4400UD-MV-US, Serial #T2520600152) with subcontracted employees, did not verify that electrical energy had been de-energized, and isolated, prior to commencing maintenance activities. This condition exposed employees and subcontracted employees to arc flash explosion hazards.