Violation Detail
Standard Cited: 19260651 J01 Specific Excavation Requirements.
Inspection Nr: 1813371.015
Citation: 01002
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $6,621.00
Current Penalty: $6,621.00
Issuance Date: 07/25/2025
Nr Instances: 2
Nr Exposed: 2
Abatement Date:
Gravity: 5
Report ID: 0420600
Contest Date: 08/21/2025
Final Order:
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | C: Contested | 09/24/2025 | $6,621.00 | Serious | ||
Penalty | Z: Issued | 07/25/2025 | $6,621.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.651(j)(1):Adequate protection was not provided to protect employees from loose rock or soil that could pose a hazard by falling or rolling from an excavation face: a.) At the worksite, located near Hidden Hammock Loop Parrish, FL 34219; On or about 3/25/25, the employer exposed employees to engulfment and crushing hazards in that employees were conducting sewer line repair operations within an excavation approximately 16ft in depth with an excavation face wall unstable and fissuring.