Violation Detail
Standard Cited: 19260651 C02 Specific Excavation Requirements.
Inspection Nr: 1803361.015
Citation: 01002
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $16,550.00
Current Penalty: $15,000.00
Issuance Date: 04/08/2025
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 04/18/2025
Gravity: 10
Report ID: 0316400
Contest Date:
Final Order: 04/22/2025
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 04/22/2025 | $15,000.00 | 04/18/2025 | Other | |
Penalty | Z: Issued | 04/08/2025 | $16,550.00 | 04/18/2025 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.21(b)(2): The employer did not instruct each employee in the recognition and avoidance of unsafe conditions and the regulations applicable to his/her environment to control or eliminate hazards or other exposure to illness or injury: a) Triton Construction: On or about February 10, 2025, the employer did not adequately have procedures to instruct employees on the hazards associated with excavations. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photograph or video evidence of abatement or other written records.