Violation Detail
Standard Cited: 19100303 G01 I A General.
Inspection Nr: 1801999.015
Citation: 01002
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $7,516.00
Current Penalty: $4,143.00
Issuance Date: 06/13/2025
Nr Instances: 1
Nr Exposed: 2
Abatement Date:
Gravity: 5
Report ID: 0524500
Contest Date:
Final Order: 06/27/2025
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 06/27/2025 | $4,143.00 | Other | ||
| Penalty | Z: Issued | 06/13/2025 | $7,516.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.303(g)(1)(i)(A): For electric equipment operating at 600 volts, nominal, or less to ground, and likely to require examination, adjustment, servicing, or maintenance while energized, the depth of the working space in the direction of access to live parts (as measured from the live parts where they were exposed or from the enclosure front or opening where they were enclosed) was less than indicated in Table S-1 of Subpart S of Part 1910: On or about February 4, 2025, employees in the Foundry Department were exposed to injury and not able to access the E-1 WEST and E-1 EAST electric panels due to stored equipment blocking the panels.