Violation Detail
Standard Cited: 19100219 F03 Mechanical power-transmission apparatus.
Inspection Nr: 1798380.015
Citation: 01002
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $11,705.00
Current Penalty: $5,852.00
Issuance Date: 04/09/2025
Nr Instances: 1
Nr Exposed: 20
Abatement Date: 04/29/2025
Gravity: 5
Report ID: 0522300
Contest Date:
Final Order: 05/07/2025
Related Event Code (REC): C
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/07/2025 | $5,852.00 | 04/29/2025 | Other | |
| Penalty | Z: Issued | 04/09/2025 | $11,705.00 | 04/29/2025 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.219(f)(3):Sprocket wheels and chains which were seven (7) feet or less above floors or platforms were not enclosed: On or about January 14, 2025, the employer did not ensure that effective machine guarding was in place on the overhead conveyor system chain and sprocket area. The ingoing nip point where the chain met the sprocket was not guarded to protect employees from reaching into the hazardous area.