Violation Detail

Standard Cited: 19100119 D03 I B Process safety management of highly hazardous chemicals.

Inspection Nr: 1797370.015

Citation: 01002

Citation Type: Serious

Abatement Status: Abatement Completed

Initial Penalty: $7,093.00

Current Penalty: $16,550.00

Issuance Date: 06/13/2025

Nr Instances: 5

Nr Exposed: 10

Abatement Date: 01/22/2026

Gravity: 1

Report ID: 0523400

Contest Date: 07/08/2025

Final Order: 12/22/2025

Related Event Code (REC):

Emphasis:

Substance: 0170


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty F: Formal Settlement 12/22/2025 $16,550.00 01/22/2026 Serious  
Penalty C: Contested 07/08/2025 $7,093.00 07/11/2025 Serious  
Penalty Z: Issued 06/13/2025 $7,093.00 07/11/2025 Serious  

Text For Citation: 01 Item/Group: 002 Hazard:

1910.119(d)(3)(i)(B) Piping and instrument diagrams (P&ID's); (a) Anhydrous Ammonia Refrigeration Systems: On or about January 13, 2025, inspection of the piping system on the roof identified that piping was inaccurately labeled and piping and instrumentation diagrams (P&ID)'s R106 & R105 did not reflect the current piping configuration associated with DR, HGD, HTRS, and the HTRL lines. The HTRL lines were label duplicatively and did not have unique identification. The P&IDs R106 & R105 did not have the correct nomenclature for each line in the system in that the 2 HTRL lines were label the same and could not be differentiated on the P&ID's. (b) Anhydrous Ammonia Refrigeration Systems: On or about January 13, 2025, inspection of the piping system on the roof, identified that P&IDs R106 & R105 did not reflect current piping configuration associated with DR, HGD, HTRS, HTRL, & HTRL. P&IDs R106 & R105 did not have the correct nomenclature for each line in the system in that the DR was represented as HTRS. (c) Anhydrous Ammonia Refrigeration Systems: On or about January 13, 2025, inspection of the piping system on the roof, identified that P&IDs did not reflect current piping configuration associated with DR. The DR was missing in P&ID R106 for the AU1, AU5, AU7, and AU8. (d) Anhydrous Ammonia Refrigeration Systems: On or about January 13, 2025, inspection of the piping system on the roof, identified that P&IDs did not reflect current piping configuration associated with LLTS. The LLTS was removed in the expansion of the system in 2013. (e) Anhydrous Ammonia Refrigeration Systems: On or about January 13, 2025, inspection of the piping system on the roof, identified that P&IDs R106 & R105 did not reflect current piping configuration associated with DR, HGD, HTRS, HTRL, & HTRL. P&IDs R106 & R105 did not have any diameter values for each line in the system.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.