Violation Detail
Standard Cited: 19100179 J02 I Overhead and gantry cranes.
Inspection Nr: 1787012.015
Citation: 01002
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/03/2025
Nr Instances: 1
Nr Exposed: 2
Abatement Date:
Gravity: 5
Report ID: 0213100
Contest Date:
Final Order: 04/25/2025
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 04/03/2025 | $0.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.179(j)(2)(i): All functional operating mechanisms for maladjustment interfering with proper operation were not inspected for defects at intervals as defined in paragraph (j)(1)(ii) of this section or as specifically indicated, including observation during operation for any defects which might appear between regular inspections: (a) Building 135, D Bay - On or about November 07, 2025 employees were required to operate a P&H overhead crane to lift a 5,500 pound M284/M776 breech block cannon. The employer did not ensure that daily inspections of the P&H overhead crane were conducted prior to use.
Translate