Violation Detail
Standard Cited: 19260451 D02 General requirements.
Inspection Nr: 1781065.015
Citation: 01002
Citation Type: Serious
Abatement Status:
Initial Penalty: $10,641.00
Current Penalty: $10,641.00
Issuance Date: 03/21/2025
Nr Instances: 6
Nr Exposed: 6
Abatement Date: 04/16/2025
Gravity: 5
Report ID: 0523400
Contest Date: 04/21/2025
Final Order:
Related Event Code (REC): A
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | C: Contested | 04/24/2025 | $10,641.00 | 04/16/2025 | Serious | |
Penalty | Z: Issued | 03/21/2025 | $10,641.00 | 04/16/2025 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.451(d)(2): Suspension scaffold outrigger beams were not restrained to prevent movement: (a) On or about October 10, 2024, and at times prior, at 901 North 9th Street, Milwaukee, WI 53203, the employer had not set up the suspension scaffold outrigger beam to prevent movement, in that the Skyclimber 5" by 5" I-beam were not crossed braced to the Safeway scaffold below to prevent rotation of the I-beams.