Violation Detail
Standard Cited: 19100333 B02 II A Selection and use of work practices
Inspection Nr: 1773825.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $13,005.00
Current Penalty: $7,803.00
Issuance Date: 02/28/2025
Nr Instances: 1
Nr Exposed: 15
Abatement Date: 03/26/2025
Gravity: 5
Report ID: 0420600
Contest Date:
Final Order: 03/25/2025
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 03/25/2025 | $7,803.00 | 03/26/2025 | Serious | |
| Penalty | Z: Issued | 02/28/2025 | $13,005.00 | 03/26/2025 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.333(b)(2)(ii)(A): Safe procedures for deenergizing circuits and equipment were not determined before circuits or equipment are deenergized. a. At the mixing plant building: On or about September 4, 2024, the employer exposed employees to a 120-voltage electrical hazard, in that the employer did not identify all electric energy sources to be deenergized prior the replacement or maintenance of the IMP Screw Drive electrical circuit disconnect.
Translate