Violation Detail
Standard Cited: 19100119 D03 I F Process safety management of highly hazardous chemicals.
Inspection Nr: 1759654.015
Citation: 01002
Citation Type: Serious
Abatement Date: 02/03/2025
Initial Penalty: $6,913.00
Current Penalty: $6,913.00
Issuance Date: 01/02/2025
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC):
Gravity: 1
Report ID: 0627100
Contest Date: 01/24/2025
Final Order:
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | C: Contested | 01/28/2025 | $6,913.00 | 02/03/2025 | Serious | |
Penalty | Z: Issued | 01/02/2025 | $6,913.00 | 02/03/2025 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.119(d)(3)(i)(F): Process safety information (PSI) pertaining to the equipment in the process did not include design codes and standards that were employed: On or about July 3, 2024, at General Dynamics Ordnance and Tactical Systems (GD-OTS) facility in Hampton Arkansas, the employer did not document employed design codes and standards for process safety management (PSM) covered process equipment, such as but not limited to FillPro loader.