Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
This violation item has been deleted.
Inspection Nr: 1744718.015
Citation: 01002
Citation Type: Serious
Abatement Status:
Initial Penalty: $5,323.00
Current Penalty: $0.00
Issuance Date: 08/20/2024
Nr Instances: 1
Nr Exposed: 26
Abatement Date: 09/16/2024
Gravity: 1
Report ID: 0111500
Contest Date:
Final Order: 11/18/2024
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 11/18/2024 | $0.00 | 09/16/2024 | Serious | |
Penalty | Z: Issued | 08/20/2024 | $5,323.00 | 09/16/2024 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirements of this standard are being followed: Facility: On or about April 30, 2024, the employer had not conducted a periodic inspection of the energy control procedures for the coil line.